California's high-speed train seeks new path forward with federal money in doubt

A bridge under construction crossing a highway where one side is dry land and the other side is full with greenery.
The Tied Arch Bridge construction site in Fresno County.
(
Courtesy of California High-Speed Rail Authority
)

Congress has cut federal funding for public media — a $3.4 million loss for LAist. We count on readers like you to protect our nonprofit newsroom. Become a monthly member and sustain local journalism.

Hundreds of miles from Los Angeles and San Francisco, the first leg of California's high-speed rail line is rising above the almond trees and grape vines of the Central Valley.

This summer, construction workers put the final concrete girder in place for the Hanford Viaduct, an elevated structure more than 6,300 feet long. It's part of a 119-mile stretch around Fresno and Bakersfield that's already under construction, and where crews could begin laying track as soon as next year.

"This is all doable. This is all buildable," said Ian Choudri, the CEO of the California High-Speed Rail Authority. "The hardest part is over."

If you want to ride on a train traveling more than 180 mph, you can find one in Europe. Also China, Japan, Indonesia, Turkey, even Morocco. One country where you cannot ride such a train is the United States.

Support for LAist comes from

California is trying to change that. But the state's ambitious high-speed rail project faces an uncertain future as the Trump administration tries to cancel billions of dollars in federal funding.

Choudri took the top job at California's high-speed rail authority last year after decades in the private sector, including high-speed rail projects in France and Spain. He readily acknowledges that the California project has made mistakes — but he insists the authority has learned from them.

A bridge under construction crossing a railroad track where one side has rows of trees and the other side is partially dry grass.
The Hanford Viaduct stretches more than 6,300 feet in Kings County, Calif.
(
Courtesy of California High-Speed Rail Authority
)

"Bureaucracy and regulations created the nightmare," Choudri said in an interview at the authority's headquarters in Sacramento. "That caused this program to start on the wrong foot."

Those missteps are well documented: rushing to begin construction before all the land was acquired, committing too early to the wrong routes, endless environmental reviews.

After more than 15 years in development, a high-speed train connecting San Francisco and Los Angeles remains a distant goal. The project is years behind schedule and billions over budget. Critics, including the Trump administration, call it a boondoggle.

Support for LAist comes from

"This is the definition of government incompetence and possibly corruption," said U.S. Transportation Secretary Sean Duffy in a video announcing that his department would seek to revoke $4 billion in federal grants for the project. "That's why we're pulling the plug."

Duffy noted that the area under construction now will only serve the Central Valley — stopping well short of the original plan to connect the line with San Francisco and traffic-clogged Southern California.

"No more federal funds for this high-speed train to nowhere," Duffy said.

Federal transportation officials concluded that the project has "no viable path" forward. But the high-speed rail authority disputes that.

California is suing to stop the Trump administration from revoking those federal grants. And Choudri is doing all he can to push back on the "train to nowhere" narrative.

The authority released an updated report on the project last month, laying out a new strategy that could eventually connect the Central Valley to the southern edge of the San Francisco Bay Area and the northern edge of Greater Los Angeles by 2038 — if California lawmakers can find more money to finance the extensions.

Support for LAist comes from
A man with light medium skin tone wearing a checkered suit and dress shirt standing next to a window with closed blinds.
Ian Choudri, CEO of the California High-Speed Rail Authority, in his office in Sacramento.
(
Joel Rose
/
NPR
)

And CEO Ian Choudri has invited Trump administration officials to see the progress in person.

"I just want people to come and visit, and just go drive around and see the 70 miles that is already built," Choudri said. "It's not hypothetical stuff. It's there."

That infrastructure is already having a positive impact in places like Fresno, the fifth-largest city in California, where the rail authority recently finished one of several new tunnels under the future high-speed rail line and station.

Fresno city councilmember Miguel Arias says the Tulare Street Underpass is helping reconnect the historically disadvantaged Chinatown neighborhood with downtown Fresno.

"It's gonna permanently reconnect the two neighborhoods back," Arias said. "That's been a huge significant change for us as a city. Something we could have never done on our own."

But the Tulare Street Underpass took seven years to build. Garth Fernandez, the regional director for the high-speed rail authority, says it's a good example of why this project is taking so long.

Support for LAist comes from
A man with medium skin tone, wearing a safety vest on top of a dark blue shirt, smiles as she stands in a walkway underneath two overpasses.
Garth Fernandez, the Central Valley regional director for the California High-Speed Rail Authority, in the Tulare Street Underpass in Fresno.
(
Joel Rose
/
NPR
)

"We weren't ready to go to construction. We didn't have the right of way. We didn't have agreements in place. We didn't have utilities out of the way," Fernandez said.

That's just one of 60 at-grade crossings in the Central Valley alone — each with its own local community making its own local demands. Fernandez says the authority has learned to streamline the process.

"The next phases of the project are going to be significantly different because of all the lessons we learned," Fernandez said.

But some Californians may have already lost patience.

"I just don't think taxpayers are going to support it at the end of the day," said Lee Ohanian, a professor of economics at the University of California, Los Angeles, and a senior fellow at the Hoover Institution, a conservative-leaning think-tank. "I'm not sure LA to San Francisco was ever realistically on the table once the costs rose so much."

Even supporters of high-speed rail are skeptical that the project can recover from its early stumbles.

"At this point, the high-speed rail authority is run by professionals. It's just that all the bad decisions are kind of baked in," said Alon Levy, a fellow at the NYU Marron Institute who studies the costs of big public transportation projects.

Levy still thinks high-speed rail between San Francisco and Los Angeles is a good idea. But they worry that past mistakes will make it difficult to ever connect the state's biggest population centers in under three hours, as the project's leaders originally promised.

"It is kind of frustrating how one bad project like this can poison the entire idea for decades," Levy said.

But rail authority CEO Ian Choudri thinks Californians are still on board. He compares the effort to other ambitious infrastructure projects like the interstate highway system, or the Big Dig in Boston, that also came in late and over budget.

"Every time we do big initiatives, the results take time to get there," Choudri said. And he insists the project will continue — with or without federal support. "We will make progress. Regardless, we are moving forward."

Copyright 2025 NPR

As Editor-in-Chief of our newsroom, I’m extremely proud of the work our top-notch journalists are doing here at LAist. We’re doing more hard-hitting watchdog journalism than ever before — powerful reporting on the economy, elections, climate and the homelessness crisis that is making a difference in your lives. At the same time, it’s never been more difficult to maintain a paywall-free, independent news source that informs, inspires, and engages everyone.

Simply put, we cannot do this essential work without your help. Federal funding for public media has been clawed back by Congress and that means LAist has lost $3.4 million in federal funding over the next two years. So we’re asking for your help. LAist has been there for you and we’re asking you to be here for us.

We rely on donations from readers like you to stay independent, which keeps our nonprofit newsroom strong and accountable to you.

No matter where you stand on the political spectrum, press freedom is at the core of keeping our nation free and fair. And as the landscape of free press changes, LAist will remain a voice you know and trust, but the amount of reader support we receive will help determine how strong of a newsroom we are going forward to cover the important news from our community.

Please take action today to support your trusted source for local news with a donation that makes sense for your budget.

Thank you for your generous support and believing in independent news.

Chip in now to fund your local journalism
A row of graphics payment types: Visa, MasterCard, Apple Pay and PayPal, and  below a lock with Secure Payment text to the right
(
LAist
)

Trending on LAist