Regulators know PG&E, Edison are slow to hook up solar. Why are there no penalties?

A worker wearing a white helmet using a drill to install a solar panel on a roof with trees in the background.
A worker installs solar panels in Hayward on April 29, 2020.
(
Ben Margot
/
AP Photo
)

Congress has cut federal funding for public media — a $3.4 million loss for LAist. We count on readers like you to protect our nonprofit newsroom. Become a monthly member and sustain local journalism.

The state’s two largest utilities routinely drag their feet connecting solar panels to the electric grid, missing state-mandated deadlines as much as 73% of the time, according to a complaint filed to regulators by solar advocates.

The complaint filed by a solar energy advocacy group urges the California Public Utilities Commission to hold utilities accountable when they fail to meet such deadlines. The commission is formally reviewing it.

The advocates have complained for years that such delays hinder California’s transition to renewables. State utility regulators are separately revisiting the process for connecting rooftop solar to the grid, including examining whether and how the utility commission should require utilities to comply with the timelines it established years ago.

But the commission has yet to reprimand utilities for regularly missing these deadlines.

Support for LAist comes from

“The rule is there, but the commission hasn’t chosen to enforce [it],” said Kevin Luo, policy and market development manager for the California Solar & Storage Association, a group advocating for the adoption of solar energy that filed the complaint.

The rule is there, but the commission hasn’t chosen to enforce [it].
— Kevin Luo, California Solar & Storage Association

When Californians add solar panels to their rooftops, they begin a complex “interconnection” process led by the utilities to ensure the array is correctly installed and able to provide power for both the customer and the grid, which receives power the customer does not use. For each interconnection step, the utility is allotted a certain amount of time, ranging from five business days to 90 calendar days.

The timelines for several of the more extensive steps – including design, construction and installation – were clarified in a 2020 decision after solar panel owners complained that California’s major investor-owned utilities were blowing their deadlines.

The delays can have significant financial consequences for panel owners, widening the period after they have laid out money for solar cells but before they see a reduction in their power consumption or payments from selling excess solar power back to utilities.

Pacific Gas & Electric, Southern California Edison, and San Diego Gas & Electric all report their compliance with these timelines on a quarterly basis. The reporting is for projects over 30 kilowatts, which are often for businesses, not residential homes, and account for the majority of solar projects.

Support for LAist comes from

These data show that PG&E and Edison routinely exceed the allotted windows.

In the complaint, filed in late August, the California Solar & Storage Association noted the utilities take longer than permitted to connect customers between 19% and 73% of the time, depending on which stage of the process is examined.

For example, the utilities are given 10 business days to acknowledge someone’s request for interconnection – PG&E’s median time for this step was 20 days, with its longest being 245 days. One of the most crucial steps is a system impact study, which looks at how the addition of a customer’s solar array will affect the grid and identifies any potential issues with hookup. PG&E kept to its timeline 49% of the time, while Edison met its deadline 43% of the time, according to the complaint.

San Diego Gas & Electric typically meets its deadlines and wasn’t included in the solar association’s complaint about timeliness.

PG&E spokesperson Mike Gazda responded to the complaint by stating that “PG&E is a strong advocate for solar energy and has interconnected nearly 900,000 solar customers—more than any other U.S. utility—to support customers who have made the choice to go solar, strengthen California’s energy grid and reduce our state’s carbon footprint. We look forward to addressing the latest claims made by the solar gorup through the appropriate regulatory channels.”

Edison spokesperson Jeff Monford said the company takes “complaints seriously and [is] working with the California Public Utilities Commission to thoroughly address any issues related to our interconnection processes.”

Utilities have previously said that delays can be caused by permitting issues, unfamiliar new technologies, or other agencies needing to be involved.

Support for LAist comes from

So what happens when they break the rules?

The utilities commission declined to lay out specific penalties when it clarified the timelines in 2020. It rejected a recommendation from a working group including industry representatives and consumer advocates to “clearly indicate that financial penalties” could happen if a utility fails to meet the timelines on 95% of projects.

“The commission must first determine whether timeline certainty is improving,” the decision said. Regulators could set out penalties in the future “if it determines such a construct would support timely interconnection.”

The commission declined to comment because the case is an “ongoing adjudicatory proceeding,” Adam Cranfill, spokesperson, said.

Without some kind of punishment, advocates argue, there’s not only no incentive for utilities to follow the rules, there’s a disincentive because of how the money flows.

“From their perspective, solar and storage is competition for them,” Luo said. “Having people with their own solar and storage reduces the need to continually expand the grid and build out transmission lines.”

California’s rooftop solar industry has been mired in controversy in recent years because of the state’s “net energy metering” program, which governs how much utilities are required to pay solar customers for extra energy their panels generate. The program is meant to incentivize adopting renewable energy sources and offset the significant cost of rooftop solar, but utilities argued it creates an unfair cost burden for those without solar who pay more for costs such as grid maintenance. As a result, the current iteration of the program pays out significantly less than prior versions.

Support for LAist comes from

Three environmental groups sued over the change, and the California Supreme Court ruled last month that the lower courts should reexamine the case’s details instead of deferring to utility regulators.

This article was originally published on CalMatters and was republished under the Creative Commons Attribution-NonCommercial-NoDerivatives license.

As Editor-in-Chief of our newsroom, I’m extremely proud of the work our top-notch journalists are doing here at LAist. We’re doing more hard-hitting watchdog journalism than ever before — powerful reporting on the economy, elections, climate and the homelessness crisis that is making a difference in your lives. At the same time, it’s never been more difficult to maintain a paywall-free, independent news source that informs, inspires, and engages everyone.

Simply put, we cannot do this essential work without your help. Federal funding for public media has been clawed back by Congress and that means LAist has lost $3.4 million in federal funding over the next two years. So we’re asking for your help. LAist has been there for you and we’re asking you to be here for us.

We rely on donations from readers like you to stay independent, which keeps our nonprofit newsroom strong and accountable to you.

No matter where you stand on the political spectrum, press freedom is at the core of keeping our nation free and fair. And as the landscape of free press changes, LAist will remain a voice you know and trust, but the amount of reader support we receive will help determine how strong of a newsroom we are going forward to cover the important news from our community.

Please take action today to support your trusted source for local news with a donation that makes sense for your budget.

Thank you for your generous support and believing in independent news.

Chip in now to fund your local journalism
A row of graphics payment types: Visa, MasterCard, Apple Pay and PayPal, and  below a lock with Secure Payment text to the right
(
LAist
)

Trending on LAist