Lineage unlikely to meet deadline to clear 88 million pounds of rotting food from Boyle Heights
The deadline set by L.A. Mayor Karen Bass for the removal of all rotting food from the Lineage Logistics cold storage facility in Boyle Heights is fast approaching.
Bass reiterated on Thursday to The LA Local that all of the approximately 88 million pounds of food that had been stored inside when the facility caught fire in June is expected to be removed by Friday.
City Councilmember Ysabel Jurado, who represents District 14 where Lineage is located, said in a press release Thursday afternoon that the cleanup efforts will likely not meet the deadline.
“I fully support the Mayor leveraging all the enforcement, cost-recovery, and accountability tools available to make clear that when the City establishes a public-health deadline, corporations are expected to meet it — and there are consequences when they do not,” Jurado said in the statement.
The company’s reports on the cleanup progress, similarly, have not appeared to be on pace with meeting that deadline. And some residents believe the putrid air they’ve had to live with for months will linger indefinitely despite the bureaucratic goal posts being met or moved.
Here’s what we know about the final phase of cleanup.
What is the deadline?
Soon after a fire broke out on the roof of the 500,000-square-foot cold storage facility on Los Palos Street on June 17, the managers cut the power to the two massive refrigerated rooms in the building. While firefighters took about a week to contain the blaze, the millions of pounds of food inside quickly began to rot in the summer’s heat.
Bass on June 29 issued an executive order requiring the removal of all remaining food in 45 days, or Friday, Aug. 14. Food cleanup began in early July.
Meanwhile, residents of Boyle Heights, East L.A. and several other neighboring communities who were left to deal with the putrid odors, have made more than 4,000 air quality complaints to regulators since early July.
It’s not the only deadline Lineage Logistics faces.
The South Coast Air Quality Management District, which regulates air pollution in the region, issued 19 notices of violation alleging the odors created a public nuisance. Last week, the agency ordered the company to meet dozens of cleanup and air quality control standards, including enforceable requirements for food removal and full facility cleaning.
That agency set a separate deadline of weeks for the food and other material to be removed before the remaining freezer room is fully sanitized.
What’s been cleaned up so far?
The freezer that was extensively damaged by fire has been cleared. The remaining freezer held the vast majority of the rotting food that has been polluting the air in nearby neighborhoods.
Lineage Logistics has for weeks reported on its website about its progress toward 100% cleanup.
Residents can get a sense of their pace for cleanup by tracking their reports:
- Aug. 7: 85% of food waste had been removed
- Aug. 11: 92% of “bulk food cleanup” was completed
- Aug. 12: 93% of food had been cleaned up
It’s unclear how exactly Lineage is arriving at these measurements and how the city or some other agency is independently verifying this progress.
Will they meet the deadline?
Lineage is clearing between 1% and 1.5% of food each day, according to their progress reports. This roughly aligns with the weekly goal AQMD ordered Lineage to maintain, 10% or 8.8 million pounds of food removed each week.
At that pace, it is unlikely they’ll be able to remove the remaining 7% of food waste in the next 24 hours.
Unless they significantly accelerate, this puts full food cleanup somewhere into next week. That revised timeline better aligns with the one Dominic DiCarlo, vice president of global safety and compliance for Lineage, outlined during the AQMD hearing last week.
DiCarlo added that the company expects to spend between $80 and $100 million on the cleanup and related expenses, which has been described as continuing around the clock.
Lineage did not respond to The LA Local’s request for more information about their progress toward the mayor’s deadline on Thursday.
What happens if they blow the deadline?
Jurado reported Thursday that Lineage would not meet the deadline, and expressed frustration with what residents have had to deal with.
Jurado’s statement reflected this: “For nearly two months, families in Boyle Heights have lived with unbearable odors, flies and pests, truck traffic, uncertainty, and disruption to their homes, businesses, and daily lives. They were told there was a deadline, and they had every right to expect that deadline to mean something.”
Bass’ executive order does not provide details on what will happen if Lineage does not meet the Friday deadline for clean up. Her office told The LA Local that it will provide more information on Thursday about the consequences if the deadline is not met.
She is also hosting a virtual community meeting Thursday about the cleanup efforts.
Bass was among several local elected officials who had pushed AQMD to levy fines on Lineage for its air pollution violations, which it did not do. She has pushed city agencies to prevent Lineage from reconstructing the facility and continuing its business there. Local lawmakers have also introduced legislation that could increasingly regulate similar businesses in the future.
AQMD can levy penalties if Lineage does not meet its deadlines for cleanup in the coming weeks.
What are residents saying?
Residents on Prado Street were still hopeful Thursday that cleanup would be finished by the deadline.
“Ojalá,” that’s what Irma Soto said when she was asked if she believed workers would finish in time. “I hope they finish so this could all end.”
“It smells horrible,” she added as the stench emanated from the neighborhood early Thursday afternoon.
Soto said she’s been seeing more trailers picking up debris lately. Her neighbor said there appears to be more nighttime work near the facility recently.
“Who knows if they’ll finish, but they are working faster,” the neighbor said.
The post Lineage unlikely to meet deadline to clear 88 million pounds of rotting food from Boyle Heights appeared first on LA Local.