Feds again delay San Onofre nuclear plant restart decision

The San Onofre Nuclear Generating Station has been offline since a radioactive steam leak in January 2012. U.S. Sen. Barbara Boxer wants the Justice Department to investigate if California utility executives deceived federal regulators about an equipment swap at the San Onofre nuclear power plant that eventually led to the radiation leak. (Photo: A cyclist rides past the San Onofre Nuclear Power Plant on April 6, 2012.)
The San Onofre Nuclear Generating Station has been offline since a radioactive steam leak in January 2012. The Nuclear Regulatory Commission has again delayed a decision on the proposed restart of the plant, which is on the seaside border of San Diego and Orange counties. (Photo: A cyclist rides past the San Onofre Nuclear Power Plant on April 6, 2012.)
(
Grant Slater/KPCC
)

One year ago, Congress defunded public media. Now that we're 100% community funded, please become a sustaining member or increase your existing membership today.

Federal regulators have indefinitely delayed a decision on the proposed restart of the offline San Onofre nuclear power plant in Southern California, raising new questions Monday about whether the twin reactors will produce electricity again.
    
The plant, on the seaside border of San Diego and Orange counties, has been dark since January 2012, after a small radiation leak led to the discovery of unusual damage to hundreds of tubes that carry radioactive water.
    
Operator Southern California Edison wants permission to restart the Unit 2 reactor and run it at reduced power in hopes of stopping vibration and friction that was blamed for damaging tubing.
    
The Nuclear Regulatory Commission delayed several earlier target dates for a ruling, with officials recently projecting a June announcement. But its website on Monday listed no date for a restart decision - only "to be determined."
    
Agency spokesman Victor Dricks had no comment.
    
Last week, the NRC's Atomic Safety and Licensing Board sided with environmentalists who have called for lengthy hearings on the restart plan after concluding that firing up the plant would allow Edison "to operate beyond the scope of its existing license."
    
A statement from SCE spokeswoman Jennifer Manfre noted that NRC Chair Allison Macfarlane indicated earlier that no decision would be made until at least mid-June on the company's request to change its operating license to run at lower power, a critical step in the restart plan.
    
"SCE continues to adhere to the established regulatory process," the statement said. The company "cannot restart Unit 2 until the NRC says that it is safe to do so."
    
Last month, SCE's parent, Edison International, raised the possibility of retiring the plant if it can't get one reactor running later this year. The company also disclosed that costs tied to the long-running shutdown had hit $553 million.
    
Edison is facing a tangle of regulatory obstacles that include a separate state investigation into who should pay for the trouble - customers or shareholders.
    
Meanwhile, anti-nuclear activists and some lawmakers have said restarting the plant would lead to a disaster.
    
Friends of the Earth, an advocacy group challenging the restart, believes no decision can be made "until all the safety issues raised by the board are addressed," spokesman Shaun Burnie said in an email.
    
Even with San Onofre sidelined, state power officials predict that there should be adequate power supplies in California this summer, but heat waves or wildfires that damage transmission lines could lead to potential shortages.

The 2013 summer assessment released May 6 by the California Independent System Operator Corporation showed there would be an adequate supply of electricity for most of California, the summer assessment noted that the reliability risks to southern Orange and San Diego counties are “marginally more challenging” this summer, but still within planning standards.

If the San Onofre Nuclear Generating Station does not restart, it would be the second consecutive summer without power from the plant. 
    
The problems at San Onofre center on steam generators that were installed during a $670 million overhaul in 2009 and 2010. After the plant was shut down, tests found some generator tubes were so badly eroded that they could fail and possibly release radiation, a stunning finding inside the nearly new equipment.
    
San Onofre is owned by SCE, San Diego Gas & Electric and the city of Riverside.

One year ago, Congress voted to defund public media, eliminating a critical $1.7 million from our budget every year going forward. But they couldn’t silence us, and we’re not going anywhere. LAist is now 100% community funded and that means we’re taking our future into our own hands and turning to you to keep local reporting strong.

You come to LAist because you want independent reporting and trustworthy local information. Our nonprofit newsroom doesn’t answer to shareholders looking to turn a profit. Instead, we answer to you and our communities. We are free to follow facts wherever they lead and to hold power to account without fear or favor. Our only loyalty is to our readers and listeners and our mission: to inform, engage, and strengthen Southern California’s communities.

If this story helped you, please become a monthly member today to help sustain this mission. It just takes 1 minute to donate below.
Senior Vice President News, Editor in Chief

Make your tax-deductible donation today