MacArthur Park fence construction to begin Nov. 16
Construction of the green metal fence around MacArthur Park will begin Monday, Nov. 16, with work scheduled to continue through fall 2027.
The city announced the start date Nov. 4, saying crews will install an 8-foot fence around the park’s perimeter. Nearby residents and businesses can expect some noise, dust and vibration during construction, although the city said mitigation measures will be in place.
Crews will work Monday through Friday from 7 a.m. to 3:30 p.m., and the park will remain open while crews are working.
The fence is the city’s latest attempt to tackle longstanding problems at MacArthur Park, including drug use, homelessness and crime.
The city first approved plans for the fence in October 2025, and the proposal has since drawn both support and criticism from residents and community groups.
Some say they hope the fence will make the park safer, while others question whether it will actually improve conditions there. Police and city officials say the fence will give them more control over the space and make it easier to enforce the law.
Ana Luz Vazquez, a street vendor near MacArthur Park, said her main concern about the fence is what will happen to the unhoused people who stay in the park throughout the day and whether the city plans to address that issue directly.
She is also concerned that construction during the day could affect her ability to work because of traffic, less parking availability and loud noise.
Vazquez said she would prefer construction to take place at night so it would have less of an impact on street vendors.
“If they’re working in the day then how are we supposed to come here and who is going to help us survive,” Vazquez said.
Construction will happen in two phases
Phase 1
- Alvarado St. from W. 6th St. to Wilshire Blvd.
- S. Park View St. from Wilshire Blvd. to W. 6th St.
- Wilshire Blvd. from Alvarado St. to S. Park View St.
Phase 2
- Alvarado St. from Wilshire Blvd. to W. 7th St.
- S. Park View St. from W. 7th St. to Wilshire Blvd.
- Wilshire Blvd. from S. Park View St. to Alvarado St.
- W. 7th St. from Alvarado St. to S. Park View St.
Existing trees will be protected and monitored during the work, according to the Department of Recreation and Parks. Traffic control measures will be in place during work hours, and crews will post temporary “No Parking” signs near active work areas in advance.
Services at the park are expected to remain the same throughout construction. The schedule could change because of weather or other unforeseen circumstances, according to the city.
The city has allocated $2.3 million for the project, but officials have not said whether that will cover the full cost.
After the fence is installed, the city plans a second phase focused on adding decorative elements. Officials have said residents will have an opportunity to provide input on the design.
Residents with questions or concerns about the project can contact Recreation and Parks at RAP.PublicInfo@lacity.org or 213-202-2700.